Mawan Cross-Sea Passage is the largest cross-sea TBM tunnel in China and the first subsea tunnel in Shenzhen. In the morning of July 15th, mawan, a 15.53m diameter super-large diameter slurry balance shield machine jointly developed by CREG and CRTG, was successfully launched.

Super Large Diameter Slurry balance TBM

The TBM section of Mawan Cross-Sea Passage Project is 2,063 meters long. As the key control link of the project, the on-site assembly of 'Mawan' is of great importance. China Railway Engineering Equipment Group Co., Ltd. started assembly on April 7, 2021, and completed the work of setting tool head into shaft on May 11 through concentric peer work and sincere cooperation with the project department. 

Super Large Diameter Slurry balance TBM

'Mawan' TBM will cross the complex seabed terrain full of uneven rock strata and full-section hard rock. The subsea tunnel is located at a depth of more than 40 meters underwater, with high water pressure and rock strength, setting high requirements for equipment performance and construction technology. 


Related news / 推荐新闻 More
2024 - 10 - 02
On October 1st, the highly anticipated Macao Bridge (formerly known as the Fourth Bridge Linking Macau and Taipa) inauguration ceremony was grandly held on the banks of the Haojiang River, marking the completion and operation of the fourth cross-sea bridge connecting Macau and Taipa, built with the participation of CRHIC. Macao Bridge is the first two-way eight-lane cross-sea bridge in Macau.The M...
2024 - 08 - 06
On August 5th, five “explosion-proof” earth pressure balance TBMs for export projects in Italy passed client’s acceptance and collectively rolled off the production line at the manufacturing base of China Railway Engineering Equipment Group Co., Ltd. (CREG). The machines will be shipped to Italy for the PA-CT Phase II project on Island of Sicily and the Salerno high-speed railway project, providin...
2024 - 08 - 03
From completing the first section of the main line 23 days ahead of schedule, to entering the third phase of construction 45 days in advance, the East Coast Railway Link of Malaysia, a key project under “the belt and Road Initiative” has seen continuous acceleration thanks to the application of the CCPG500A intelligent multi-scene track-laying unit “Penglai” custom-made by China Railway Science an...
About Us China Railway Hi-Tech Industry Co., Ltd. belongs to the world's 500 strong enterprises China Railway Group Limited
Contact us
Address:Building 11, Noble center, South Fourth Ring Road, Fengtai District, Beijing,China
E-mail:inter-biz@crhic.cn
Tel:010-52265888
Fax:010-52265888
Copyright © China Railway Hi-Tech Industry Corporation Limited . All Rights Reserved
犀牛云提供企业云服务