On May 17, pre-assembly of the first tangent tower for the 275kV cross-sea transmission line project in Penang, Malaysia undertaken by China Railway Baoji Bridge (Yangzhou) Co., Ltd. under CRHIC was completed. 


Rising up to 60m and weighing 78t (excluding cross arm blocks), the tangent tower is a straight single tower structure with regular hexagonal curved section and cross section continuously decreasing from the bottom of the tower to the top. It is composed of wall panels, longitudinal stiffeners, transverse partitions, anchor plates and flanges, etc, with the maximum cross-section being 3.1m × 3.6m. The steel tower consists of 6 segments bolted with internal flanges. The overseas project team strived to make technical breakthrough and developed technologies such as appearance control of landscape power transmission tower, tightness control of internal flange connection and overall straightness control of power transmission tower. They have gained rich manufacturing experience for similar projects in the future and the power tower industry. 


Power Transmission Tower Project in Malaysia Has Made Progress


The cross-sea power transmission line in Penang, Malaysia has a total length of 8.5km and a transmission voltage of 275kV. Being a landscape and landmark engineering next to Penang Bridge 1, this project will meet the future electricity demand of Penang Island. 

About Us China Railway Hi-Tech Industry Co., Ltd. belongs to the world's 500 strong enterprises China Railway Group Limited
Contact us
Address:Building 11, Noble center, South Fourth Ring Road, Fengtai District, Beijing,China
E-mail:inter-biz@crhic.cn
Tel:010-52265888
Fax:010-52265888
Copyright © China Railway Hi-Tech Industry Corporation Limited . All Rights Reserved
犀牛云提供企业云服务